Silverstream Pipe Bridge Lift
Client: Brian Perry Civil
Project: Silverstream Bridge Lifting
Scope: Lifting, Transport, and Placement of Network Arch Bridge
Project Overview
Titan Cranes Ltd was engaged by Brian Perry Civil during the Early Contractor Involvement (ECI) phase for the Silverstream bridge project. The collaboration aimed to develop a comprehensive lifting methodology
Wellington Chiller Replacement
For: Advanced Building Services (ABS)
At: HSBC Tower , 195 Lambton Quay, Wellington Central.
Utilising the Liebherr LTM1350-6.1 Crane with 50t of counterweight (65.6M main boom with Y-guy and 48m luffing fly jib attachment) at a working radius of 32m.
Wellington Hospital - temporary ward on the roof
For: Naylor Love
At: Wellington Hospital
The project involved building a temporary ward (“decant” ward) on the hospital roof so that contractors can replace copper pipes in the existing wards at Wellington Hospital.
Prefab Pods: Eight prefabricated pods, each measuring 7m x 7m x 3.5m and weighing 14.5 tons, were built offsite in Upper Hutt by Naylor Love. These pods were designed to serve as the temporary ward.